Click here to view the "Adding a Corrective Action Report" Video
Note: Some fields may be missing or labeled differently in your database if your Admin has customized the Corrective Action Report.
Customizing your Corrective Action Report
To customize a field in your Corrective Action Report, hover next to the field name and click the pencil icon. This lets you change the label to better suit your organization’s needs.
Your Corrective Action Report can also be customized within Team Settings. For more information,
click here.
Within Team Settings, you can:
- Change the module name and icon
- Update e-signature settings
- Modify the abbreviation in the list view
- Hide or require specific fields
Can't customize the CAR? That's because your not an Admin. See Isolocity's User Permissions, here.
Creating a Corrective Action Report
Step #1
Click here to access the "CAPA" sub-menu.
Step #2
Click "Corrective Actions".
Step #3
Click "Create a Corrective Action Report".
Step #4
Complete the "Administrative Details" section by completing the following fields:
- Job #
- Batch Number
- Target Completion Date
Step #5
Complete the "Owners" section by completing the following fields:
- Owners (those who can edit the report)
- Subscribers (those who can only view the report)
- Process Owners
- QA Reviewers
- Departments
Step #6
Complete the "Source, Type and Disposition" section by completing the following fields:
- Source
- CAR Type
- Date Opened
Step #7
Click "Create Corrective Action Report" to save your progress.
Step #8
Enter in applicable "Batch Record" details.
Step #9
Complete the "Description" section by completing the following fields:
- Error Code
- Date Completed
- Assignee
- Description
- Immediate Action
Step #10
Complete the Root Cause Analysis by completing the following fields:
- Date Root Cause Occurred
- Description
- Perform a 5-Why Analysis and/or Fishbone Analysis
Step #11
Click "Add a Preventative Action" and add as many as needed.
Step #12
Assign tasks to users using the "Implementation Plan" section.
Step #13
Assign pre-set tasks to users using the "Control System Updates" section.
Step #14
Complete the "Verification Actions" section by completing the following fields:
- Preventative Action Effective?
- Due Date
- Description
Step #15
Complete the "Processes Affected" section by completing the following fields:
- Cost of Quality ($)
- Effect on Other Processes
Step #16
Complete the "Approval (Quality and Process Owner) section by adding the following approvals and/or rejections:
- Process Owner
- Quality Inspector
Step #17
Click "Save & Close" to finalize the report.
Step #18
Click here to download a PDF of your report.